✅ Answer: (D) Baseline plan
Explanation:
The baseline plan is the approved scope, schedule and cost against which progress is measured.
✅ Answer: (D) Baseline plan
The baseline plan is the approved scope, schedule and cost against which progress is measured.
✅ Answer: (B) The longest path of dependent tasks
Any delay on the critical path delays the whole project. (Here the answer is given as a number: 2 = option B.)