What does the critical path in a project schedule show?
✅ Correct answer: (B) The longest path of dependent tasks
Explanation:
Any delay on the critical path delays the whole project. (Here the answer is given as a number: 2 = option B.)
✅ Correct answer: (B) The longest path of dependent tasks
Any delay on the critical path delays the whole project. (Here the answer is given as a number: 2 = option B.)