Which document fixes the scope, cost and time of a project?
✅ Correct answer: (D) Baseline plan
Explanation:
The baseline plan is the approved scope, schedule and cost against which progress is measured.
✅ Correct answer: (D) Baseline plan
The baseline plan is the approved scope, schedule and cost against which progress is measured.